Pan African Resources (LSE: PAF) – Be-Be-Beating Hard Times, That is my Theme (Transcript)

Gold ore

Interview with Cobus Loots, CEO of Pan African Resources (LSE: PAF).

These guys get things done. Mining is never easy, mining in South Africa is far from easy, but the management team at gold producer, Pan African Resources, keep finding a way to get things done and are consistently hitting targets. Pan African is well on its way to becoming a mid-tier gold producer targeting 185,000oz per annum this year. Loots ran us through the highs and lows of the last 6 months, including the recently released operational update.

Pan African Resources has a share price of GB£0.125 and a market cap of GB£278M. It is listed on the LSE.

The key highlights from the update?

  • Pan African is on track to deliver the full-year production guidance of 185,000oz.
  • Group gold sales increased by 14.7% to 92,941oz (2018: 81,014oz).
  • The Evander 8 Shaft Pillar project development is progressing according to plan, with steady-state production planned from March 2020.

We like the tailings slant on the business. Green is very fashionable right now. Barberton Tailings Retreatment Plant produces a steady stream of gold, c. 25,000oz per annum, and the Shaft Pillar at Evander, an area of developmental focus in the near future for Pan African, could provide 20,000oz, rising to 30,000oz+ “in the years ahead.” Pan African is now mining more economically due to a strategy change: mining at the shaft rather than at deeper levels. The result is an intended sub-US$1,000 AISC for the Pillar project. Solid numbers, and in line with the rest of Pan African’s other operations. Elikhulu Tailings Retreatment Plant has had a mining feasibility study conducted that is now being independently vetted by a third party, with the view to expand it to a full feasibility study. Loots says it looks like c. 90,000oz per annum, with a 9-year life-of-mine, rising to 20 years with further resource modeling. By utilising existing infrastructure, Pan African can keep costs down and get things going quicker. This is still a little way off but could be a good addition to the portfolio.

In terms of dividends, Pan African recently released its first dividends for years. Loot states the company was recently one of the highest yielding gold dividend shares in the world. Loots states that he wants to get back there. Let’s see how things turn out.

For now, it’s full speed ahead developing the projects, overcoming issues pertaining to jurisdiction, community and environment difficulties, and getting the share price where investors will no doubt want to see it.

Interview highlights:

  • 1:34 – Operational Update: Overview of Performance Results
  • 2:45 – Producing as Expected? A Run Through the Projects
  • 8:27 – AISC and Debt: What is the Current Position and What’s to Come?
  • 9:39 – Dividends: Keeping Them Going
  • 12:40 – Troubles in Jurisdiction and Community Issues: How Will They Ensure a Smooth Run of Operations?
  • 16:14 – What Should We Look Forward to from Pan African Resources?

Watch the interview here.


Matthew Gordon: Happy New Year. I haven’t spoken to you since before Christmas, so how are you?

Cobus Loots: Thanks, Matthew. We’re good. We’ve been busy as you might have seen from the operational update.

Matthew Gordon: We have, that’s why we called you. It seems like you have had a good last 6-months. You are on target to hit 185,000oz; that puts you very much in the mid-cap territory for sure. Are you pleased with your performance?

Cobus Loots:  Yes. We believe that, certainly the performance for the first 6-months provides a solid base for us to have a very good financial year. So Elikhulu performed very well, so we produced almost 30,000oz. We are well-positioned now actually for the next 6-months to increase that to go to almost 65,000oz for the full year so that is a great performance. Barberton was down slightly, mostly as a result of underground. But we have more flexibility now so we expect a much better 6-months, going forward from Barberton. And then also, and what I think is very positive, the work that we have done in the Evander 8 Shaft pillar. This project has gone from being a liability to actually now being poised to generate attractive cash flows going forward for the next 3-years.

Matthew Gordon: Okay. If you don’t mind, can we just break down that 185,000oz that you are going to be producing. You’ve got your existing Barberton and Elikhulu, both on the tailings and the mining front, and they are going as planned? The numbers are as targeted, first of all?

Cobus Loots: Well yes.Let’s start with Elikhulu first of all which we started last year: it’s a world class project. It is USD$130M that we put into the ground. It retreats old historic mining tailings, and it has a life of 12-years at present. And it is producing at an All In Sustaining Cost of USD$650 per oz or below. I think what’s more is that we are cleaning up legacy liabilities so it ticks the box in terms of ESG, looking after the environment, etc. So it’s a great project. It’s incredibly safe. We don’t have as many employees as what we would have had underground. So, we are very happy with the performance at Elikhulu, and as I said, we expect Elikhulu to do even better over the next 6-months.

And then the Barberton complex, which is also a world class tailings business, the BTRP, we do have about 20,000oz from the BTRP at Barberton and then 80,000oz at underground. So that gives us another 100,000oz per year, from Barberton. And then as I said, the Pillar, which is a project that we commissioned at the moment at Evander, that will give us 20,000oz which then actually becomes 30,000oz and more in the years ahead.

Matthew Gordon: Okay. And you actually refer to that as a former liability. Why was that?

Cobus Loots:  We curtailed operations at 8 Shaft, so we were mining 24 level, which was very deep. With a lot of infrastructure, a lot of logistics, a huge number of employees. So we curtailed that business about 2 years ago. We actually shut it down. And then the sort of question arose: what do we do with the remaining resource? We could have quite simply terminated operations at 8 Shaft, and that would have been the end. Instead, we said, let’s have a look at this Pillar project, let’s see what sort of Gold we can get out and over what sort of timeframe and at what margin, importantly. And that’s how the 8 Shaft pillar project has happened.

Matthew Gordon: Right. So basically, it was costing you a lot of money to get Gold out of the ground. It was becoming less and less profitable, having sunk a lot of money into the ground there as well. So you are now mining more economically as a result. That’s the point of what you have done?

Cobus Loots: Well, we are ceasing operations at the bottom levels which are very expensive and we are actually starting mining right at the shaft. So we have guided, we have anticipated that the all in sustaining costs of this Pillar project to be below USD$1000, which is very attractive. And that’s in-line with the rest of our operations.

Matthew Gordon: And Cobus, can I just ask you about Egoli, because you have obviously talked about the MFS, the mine Feasibility Study has been finalised now. Where are you at with that? What should we be excited about?

Cobus Loots: Yes. It has been a very interesting project from our perspective, as you said, the Mining Feasibility Study has been done. We are actually getting the study independently vetted by a third party and then they are expanding it to a full Feasibility Study, the results of which will be available pretty much at the same time as our interim financial results.

Matthew Gordon: Right.

Cobus Loots: And yes, circa 90,000oz per year, initially life of mine 9-years but if we model for the resources, it’s anywhere from 15 to 20-years.  At a fairly limited capital number for a project of this nature because of the fact that you are utilising existing infrastructure mostly: there is a processing plant, it’s operational on surface, we have the vertical shaft that’s all done. There are turns, certainly, currently, even a conservative Gold price to be attractive. So I think, you know, watch this space in terms of Egoli and our next steps when we release our interim results.

Matthew Gordon: Okay, when does that actually…how does that ramp up? How quickly does that ramp up?

Cobus Loots: You know, we haven’t yet pushed the button on development. The key is to finalise funding. And we what we have said to shareholders, we will not do the funding in any way that is dilutive. So we are looking at potentially bring in a stream or an equity investor of sorts. Certainly, the project has dig capacity in our view also. Once we are happy with the Feasibility Study and the fact that we can manage the risks, and it is a project that we need to be doing, from a pipeline perspective, we will finalise the funding and we will certainly add a time frame in terms of development.

Matthew Gordon: Okay. So the timing is not imminent? Because when I asked you earlier about, have you plans for adding debt for this year, you said, no. So, this is not a 2020 debt solution. You are saying that will come after that?

Cobus Loots: That’s right. The ramp-up period is three years, and most of the capital is spent in the later years. And if we potentially look to get in an equity investor, or some other form of finance, then that sort of takes off the burden, certainly from ourselves. But in terms of existing operations, certainly, we will be set in terms of debt, that holds true so we are not going to look to gear up the existing operations to fund a project like this. I think that it will stand on its own two feet.

Matthew Gordon: Okay. So you have been looking at the AISC and looking at ways of reducing it. I mean, I guess it is pretty standard: getting somewhere between USD$950 USD$1,000 is where you want to be, especially in today’s Gold price. So you are obviously throwing off a lot more cash, but you’ve also had to finance a lot of the development work with debt so what is the position on that at the moment?

Cobus Loots: Well, for 6-months to December, we have managed to de-gear the balance sheet and we have guided that in the year ahead, we should see a dramatic decrease in our gearing levels. You know, that’s a product of the Pillar coming into production, so we will be steadily instating the Pillar in March. It’s a product of Elikhulu performing at a steady state and the operations at Barberton performing. Certainly, what’s helping us also is the Gold price which is performing well in US dollars and even more so in South African Rand which is the currency that we look at.

Matthew Gordon: Yes. Okay. So, if I may just touch upon this here; a lot of mid cap and a lot of large companies, they tend to borrow money, then plough it back into the ground and kind of forget about shareholders. You issued your first dividend for a couple of years recently, what are your plans for keeping that going? Are you going to give back to long-holding shareholders in your company? Or is it the plan just to reinvest into the ground?

Cobus Loots: Well, if you look at our priorities in terms of how we apply capital, we need to continue to invest in our assets. But in the past, we have managed to do so, and then also pay an attractive dividend. Certainly, up to quite recently, we were one of the highest yielding Gold dividend shares in the world. And that’s where we’d like to get back to. And I think the operating environment in terms of the robustness of our assets and the performance, and then also the Gold price, should assist us in resuming even more attractive dividends in the future. Clearly, we have stalled some of the debt that we took on to fund Elikhulu, that’s still on the balance sheet, but as I said, we anticipate that number, in terms of the gearing levels, to come down quite dramatically in the year ahead.

Matthew Gordon: Any more plans for any more debt?

Cobus Loots: Well no, there’s no need for us to incur any more debt. Also, if you look at the sort of projects that we undertake now, one obviously looks at all the return metrics including internal rate of return, MPV etc, but payback is also very important for us, so how long does it take for us to get our money back and that’s where projects like Elikhulu where regionally, we were costing a payback of 4 years on a USD$130M odd, and at this Gold price, I actually expect the pay back to be sooner. So those are the sort of projects we like to do.

Matthew Gordon: Again, it’s just trying to understand the thinking of the management team here, because you’ve got options of paying it back in 4-years or paying it back quicker, paying dividends, you know, you have got the choice of what you do with that money. Some companies like to be completely debt-free as quickly as possible; others like to maintain some kind of leverage and utilise that spare cash elsewhere to develop and grow the business, where’s your head at?  

Cobus Loots: Well look, obviously, a mining company should not be over-geared and they should have a conservative level of debt. That’s really where I think we will end up in the next 6 months or so. It also doesn’t make sense for us to have no debt. In our view, it’s not efficient from a capital allocation perspective. We think that we can pay a significant, pretty much all of our debt in the next 12 to 18 months in resumed dividends so that one is not at the expense of the other.

Matthew Gordon: Okay. So dividends; they are still in the pipeline, your shareholders will still be receiving dividends as you continue to develop the business and grow the business – perfect. Can we talk about something else though? You did highlight them and I’ll give you credit for this; you don’t shirk or hide from this, you have talked about a couple of things: there have been some community issues which have affected productivity, and also, more recently, some power issues. I know mining is mining, and it is tough, but what has gone on there and will it reoccur?  

Cobus Loots: Yes, sure. I think we have demonstrated the ability to operate successfully in South Africa. We have had community unrest and that has affected, as you pointed out, the Barberton operations in the last 6 months. We had very serious power issues with ESCOM, our South African power and utilities, in December. On top of it, we also had probably the weakest December in terms of rainfall that I can recall for the last 20-years, so that will also have affected operations. So, you know, the bottom line is that one has to plan some level of disruption to your operations and you have to robust assets that can withstand these sorts of issues, and a management team that is proactive and can anticipate when they can and then deal accordingly.

So yes, South Africa gets quite a lot of bad press I think in terms of the operating environment, and a lot of it is justified, but as you said, most mining jurisdictions have their issues.

Matthew Gordon: They do, and like I say, I give you credit for not shirking away from it or ignoring it, but like I say, ESKOM for instance – what was the issue? Is it going to reoccur? Because I look at the, again, the information that you have provided, the prices have been going up and up, which affects your margins, but how do you engage with them? How do you have conversations that give you some sort of certainty about what the future looks like?

Cobus Loots: Well sure. ESKOM has been more of an issue at Evander, our underground business, and fortunately there, we have spare capacity so we can afford to turn off a mill for a couple of hours if there is what is termed, low-shedding: so where the grid is overloaded. So we do have that capacity but what I think also, the ESKOM situation is not going to become any easier overnight. We will continue to have power shortages in South Africa for at least the next 2-years. Barberton mines is less energy intensive so it is less affected. Elikhulu doesn’t use a lot of electricity so that is less affected. And fortunately, as I said, at Evander underground, we have some spare capacity so we can afford to reduce our underground consumption for a limited period. And recently, the Minister of Mines in South Africa has come out and said that they are in the process of deregulating the private power generation. At Evander, we are completing a Feasibility Study (FS) into our solar plant that will be able to look after pretty much all of Elikhulu during the daytime. And we expect that we will be able to, over time, expand that project also. So miners are being creative about finding solutions and I think that over the medium to longer-term, we will get those solutions implemented in a way that actually makes sense for shareholders.

Matthew Gordon: Interesting. You should talk to your neighbours over the road at Bushveld by the sounds of it.

Cobus Loots: Exactly.

Matthew Gordon: Okay. Well thanks for that update. It just sounds like business as usual for you. I appreciate you being quite direct about some of the issues that you miners face, but you are consistently hitting the numbers, or exceeding the numbers, despite those problems. So you always find a way. Do stay in touch and let us know how you get on. What are the next big things that we should be looking out for?

Cobus Loots: Well, we have our interim results now being released next week, on the 18th February and that will contain more detail on performance and what we expect for the remainder of the year. And yes, as I said, we are quite positive. We have laid a solid foundation, a good base to do well. So the Rand Gold price, is pretty much the highest it has ever been so that’s a good environment for us to operate in also.

Matthew Gordon: You see that continuing do you?

Cobus Loots: We sort of try focussing on those issues we can control, but it’s always nice to have tailwinds like the Gold price.

Matthew Gordon: Light a candle, for sure. Thanks again, speak real soon.

Cobus Loots: Thanks, Matthew. Speak soon.


If you see something in this article that you agree with, or even disagree with, please let us know in the comments below.

Any advice contained in this website is general advice only and has been prepared without considering your objectives, financial situations or needs. You should not rely on any advice and / or information contained in this website or via any digital Crux Investor communications. Before making any investment decision we recommend that you consider whether it is appropriate for your situation and seek appropriate financial, taxation and legal advice.